PROPERTY NEWS - Even though it is not required to submit building plans for projects defined as 'minor building work', homeowners will still require written permission from their local authority before they start, says Adrian Goslett, regional director and CEO of RE/MAX of Southern Africa.
He points out that the National Building Regulations and Building Standards Act (Act 103 of 1977), states in part 13 (1)(a) that to undertake any building work, even if the project falls under "minor building work", the homeowner will have to apply to their local authority for authorization.
The homeowner will need to receive written permission from the building control officer, following on receipt of a permit application from the owner, before they can start their project. Written permission granted to the homeowner in terms of section 13 of the said Act therefore exempts them from submitting formal building plans.
Christo Hamman, manager of Building Control at the Hessequa Municipality, says, "We require a formal decision, in terms of section 13(1)(b) of the Act, by our Building Control section, following an application by the owner for minor building works. An approved building fee is also required. The reason we require homeowners to obtain authorisation is because of the numerous legal issues regarding, for instance, building lines, view, aesthetics, etc.
While homeowners are entitled to undertake minor building projects without formal building plans, they need to adhere to the requirements of section 13 of the Act. Obtaining authorization beforehand will ensure that they are proceeding with the project in the correct manner and erecting the building in accordance with the directions specified in such authorisation."
According to Goslett, even erecting a temporary structure as such as builder's shed will require permission from the local authority.
"It is not just the project itself that has to be given the thumbs up by the local municipality, but also all other structures that may need to be put up during the period the project takes place."
To provide permission for a temporary structure, in terms of South African National Standard (Sans) 10400: Part A23, the municipality will require the following information:
- The building's intended purpose and the length of time it will remain on the property;
- Where the homeowner intends to erect the structure;
- The availability of suitable materials from which it may be constructed.
In conclusion, Goslett says that before starting any building project, be it minor building work or otherwise, it is advisable to contact your local authority and obtain permission upfront.