Sponsored Content
BUSINESS NEWS - The public is invited to participate in the Basic Assessment process for the Sleeping Giant Main Transmission Substation (MTS), planned on Portion 2 of Farm Oorlogspoort 85 located approximately 40 km west of Xamdeboo (formerly Aberdeen) in the Dr Beyers Naudé Local Municipality, Eastern Cape.
FE Sleeping Giant (Pty) Ltd proposes to develop the Sleeping Giant MTS which will comprise 132 kV/400 kV and 400 kV/765 kV step-up transformer bays and associated infrastructure required to transmit electricity to the authorised Eskom Gamma–Grassridge 765 kV power line.
Associated infrastructure includes:
- 132 kV/400 kV transformer/s within up to 25ha High Voltage (HV) yard footprint
- 400 kV/ 765 kV transformer/s within up to 25ha HV yard footprint
- Busbars, bus couplers and bus sections
- Foundations, steel structures, platforms and equipment
- Fibre optic cables for telecommunication
- Surge and lightning protection equipment/mast
- Permanent and temporary laydown areas, Operation and Management (O&M) and Control Room buildings, security infrastructure, fencing around the development footprint
- Internal access roads
- Short access road north of the MTS site
As part of the Environmental Authorisation process, a Basic Assessment (BA) is being undertaken in accordance with the National Environmental Management Act (Act 107 of 1998). The proposed development falls within the Eastern Corridor of the Strategic Transmission Corridors.
The Basic Assessment Report will be available for public review from 3 August to 4 September, providing an opportunity for interested and affected parties to review the findings and submit written comments before the closing date of 4 September 2026.
The report can be viewed online and an electronic copy can also be made available via electronic platforms (Smash/WeTransfer/DropBox) upon request.
Community members who would like more information or wish to register as an Interested and Affected Party are encouraged to submit their name, contact details and interest in the project to Nicolene Venter at Savannah Environmental, telephone 011 656 3237 / 066 282 6913 / 060 978 8396 or email [email protected].
Public participation is an important part of the environmental assessment process, ensuring that local communities and stakeholders have the opportunity to provide input before a decision on Environmental Authorisation is made.
‘We bring you the latest Garden Route, Hessequa, Karoo news’